Projects >> U-001

U-001 - Ritschard Dam Monitoring


PI: Dr. Michael Mooney
Project Lead: Michael Mooney
Funding Source: NSF/OISE 1243539
Location: Wolford Reservoir, Kremmling, Colorado
Dates: 2011-05-04 to 2013-06-12

Project Summary

The Ritschard Dam at the Wolford Reservoir has been observed to have an ongoing displacement problem and is being studied with a variety of techniques including GBIR with Paco Gomez at University of Missouri. TLS scans of the reservoir allow for displacements to be calculated on the Ritschard Dam and evaluated against the results of the ongoing geotechnical instrumentation as well as the GBIR monitoring.

Project Sites

  1. PS01 Wolford Dam

Related Publications